Work Scheduling View:   To produce an assembly or subassembly, you  need to maintain a work scheduling view for the material.
  

  
  
  
  Production Scheduler:
  
  
  They have to be configured in SAP IMG as required.
  
  Production Scheduler is the scheduler responsible for a material in production activity control. The production scheduler determines how capacity requirements are calculated for a material during a scheduling run. You can use the Production Scheduler for the purpose of reporting, there are standard reports in SAP, that can be executed for a given production scheduler/s.
  
  Configuration Path – Production à Shop Floor Control à Master Data à Define Production Scheduler
  
  
  
  Production scheduling Profile:
  
  
  Profile that you can use to specify that certain business transactions are carried out in parallel in a production order / process order (you can, for example, create and release an order at the same time, or release an order and print the shop papers) trigger an automatic goods receipt. The production scheduling profile is copied into the order during order creation.
  
  Configuration Path – Production à Shop Floor Control à Master Data à Define Production Scheduling profile
  
  
  
  Production Version:
  
  
  Production Version defines for a material, the Bill of Material & Routing {Recipe} combination, for the production of a material, for a given Validity date & a lot size range.
  
  It is a key which determines the various production techniques according to which a material can be manufactured.
  
  See above for details in the earlier section
  
  
  
  Batch management requirement indicator:
  
  
  This indicator specifies whether the material is managed in batches at the plant for the material.
  
  Setting this indicator: Very Easy
  
  Undoing the setting: Very Hard
  
  The indicator cannot be changed if stocks exist for the given material in either the current period or in the previous period. The reason for checking the previous period is because stocks can be posted to this period when goods movements are entered. Thus in turn if stocks or requirements are open for the given material, this indicator cannot be changed.
  
  Process - To find out the activities that stop the batch management indicator from being reset you would have to go to the material master change mode (MM02) and check/uncheck the batch management indicator; on check/uncheck of this indicator the system would give an error message, if it is not able to reset the indicator. This Error message statement helps you to lead in uncheck/check the batch management indicator.  
  
  Note –  a) You would have to make the entire Stock equal to Zero.  
  
  b) You would have to reverse all the open documents that are existing for the material.
  
  c) You may also need to archive the Batch master data before you reset the batch management indicator.
  
  
  
  Under Delivery/Over delivery Tolerance:
  
  
  These are the tolerances of Goods receipt quantities against the order quantities.
  
  Unlimited over delivery tolerance is the permission to receive unlimited quantity from the order over and above the order quantity.
  
  
  Under Delivery tolerance is the permission to receive materials, in a % mentioned here, below the order quantity.
  
  For example, if your production order quantity is 100 Units and the under delivery tolerance is 10%, then on the GR of 90 Units, the system sets the DLV Status to the order.
  
  Over Delivery tolerance is the permission to receive materials, in a % mentioned here, above the order quantity.
  
  For example, if your production order quantity is 100 Units and the over delivery tolerance is 10%, then on the GR of 110 Units, the system sets the DLV Status to the order.
  
  
  
  Lot size dependant/Lot Size Independent In House times in Days:  
  
  
  The setup time a Processing times in number of days for a base quantity defines the total production time for a quantity used for MRP.
  
  The In house Production time for a lot size independent number of days is the flat time required to produce a product irrespective of base quantity. These are the timings used in MRP.
  

运维网声明 1、欢迎大家加入本站运维交流群:群②:261659950 群⑤:202807635 群⑦870801961 群⑧679858003
2、本站所有主题由该帖子作者发表,该帖子作者与运维网享有帖子相关版权
3、所有作品的著作权均归原作者享有,请您和我们一样尊重他人的著作权等合法权益。如果您对作品感到满意,请购买正版
4、禁止制作、复制、发布和传播具有反动、淫秽、色情、暴力、凶杀等内容的信息,一经发现立即删除。若您因此触犯法律,一切后果自负,我们对此不承担任何责任
5、所有资源均系网友上传或者通过网络收集,我们仅提供一个展示、介绍、观摩学习的平台,我们不对其内容的准确性、可靠性、正当性、安全性、合法性等负责,亦不承担任何法律责任
6、所有作品仅供您个人学习、研究或欣赏,不得用于商业或者其他用途,否则,一切后果均由您自己承担,我们对此不承担任何法律责任
7、如涉及侵犯版权等问题,请您及时通知我们,我们将立即采取措施予以解决
8、联系人Email:admin@iyunv.com 网址:www.yunweiku.com

所有资源均系网友上传或者通过网络收集,我们仅提供一个展示、介绍、观摩学习的平台,我们不对其承担任何法律责任,如涉及侵犯版权等问题,请您及时通知我们,我们将立即处理,联系人Email:kefu@iyunv.com,QQ:1061981298 本贴地址:https://www.yunweiku.com/thread-115544-1-1.html 上篇帖子: SAP HANA Basic information of system infranstructure 下篇帖子: SAP和ABAP内存的区别
您需要登录后才可以回帖 登录 | 立即注册

本版积分规则

扫码加入运维网微信交流群X

扫码加入运维网微信交流群

扫描二维码加入运维网微信交流群,最新一手资源尽在官方微信交流群!快快加入我们吧...

扫描微信二维码查看详情

客服E-mail:kefu@iyunv.com 客服QQ:1061981298


QQ群⑦:运维网交流群⑦ QQ群⑧:运维网交流群⑧ k8s群:运维网kubernetes交流群


提醒:禁止发布任何违反国家法律、法规的言论与图片等内容;本站内容均来自个人观点与网络等信息,非本站认同之观点.


本站大部分资源是网友从网上搜集分享而来,其版权均归原作者及其网站所有,我们尊重他人的合法权益,如有内容侵犯您的合法权益,请及时与我们联系进行核实删除!



合作伙伴: 青云cloud

快速回复 返回顶部 返回列表